Annexe Project Update April

We are now 16 weeks into the project and it is steaming ahead at a fast pace – In main due to the very hard work of the staff of 3B Construction.

The roof of the hall has been strengthened and now has the solar panels fitted and in place, the roof is also now on the annexe build and inside is starting to take shape, with it now being easy to visualise the spaces and what it is going to look like.

 annexe6.april; (500x333)       Annexe2.april (500x333)

The Board of Directors and sub-groups are working very hard in the background to finalise details on such things as the kitchen, the tearoom, retail space and furnishings required, which is taking a lot of time, but exciting at the same time!

annexe9.april (500x375)            Annexe3.april (500x333)annexe8.april (500x333)            annexe4.april (500x333)

The hall will close from Monday 16th June to allow the existing and new build to become one, and all the inside work to be completed on both areas, this should take about 5 weeks, with the hall being re-opened after this work in complete.