We are now 16 weeks into the project and it is steaming ahead at a fast pace – In main due to the very hard work of the staff of 3B Construction. The roof of the hall has been strengthened…
Annexe – Progress Report Feb 2014
What a difference a day can make – or a week for that matter! Following the sod-cutting ceremony for the new St Ninian’s Hall Annexe at the end of January, contractors 3b construction have lost no time in getting stuck…
Annexe- Progress Report. Jan 2014
At long last, we are now officially under way with the Isle’s Annexe build project. Last week, 3b construction began preparing the site, erecting security fences, installing storage containers, and getting earthmoving equipment ready, so that there would be a…
Annexe- Progress Report. 7th Jan 2014
Isle Futures are delighted to announce that 3B Construction Limited have been appointed as the successful bidder for the build contract for St Ninian’s Hall Annexe Project. During the summer, tenders for the build were issued to six contractors. The…
Progress Report. Nov 2013
Following the momentous announcement of the grant funding award for the St. Ninian’s Hall Development project by the Big Lottery in April, Isle Futures and Smith Design Associates in Dumfries, the architects appointed to manage the project build have been…